Budgeting and Scheduling Project Coursera Quiz Answer [Updated Answers‼️] 2021

Hello Peers, Today we are going to share all week assessment and quizzes answers of Budgeting and Scheduling Project course launched by Coursera for totally free of cost✅✅✅. This is a certification course for every interested students.

In case you didn’t find this course for free, then you can apply for financial ads to get this course for totally free.

Checkout this article for“How to Apply for Financial Ads?”

Coursera, a India’s biggest learning platform which launched millions of free courses for students daily. These courses are from various recognized university, where industry experts and professors teaches in a very well manner and in a more understandable way.

Here, you will find Budgeting and Scheduling Project Exam Answers in Bold Color which are given below.

These answers are updated recently and are 100% correctanswers of all week, assessment and final exam answers of Budgeting and Scheduling Project from Coursera Free Certification Course.

Use “Ctrl+F” To Find Any Questions Answer. & For Mobile User, You Just Need To Click On Three dots In Your Browser & You Will Get A “Find” Option There. Use These Option to Get Any Random Questions Answer.

Apply Now – Budgeting and Scheduling Project

Budgeting and Scheduling Project Answer

Module 2 Quiz

1.
Question 1
True or False: The term resources only refers to people, it does not include money or materials or equipment.

1 point

  • False
  • True

2.
Question 2
In our lessons the acronym RAM stands for:

1 point

  • Responsible Accountable Manageable
  • Responsibility Assignment Matrix
  • Resource Aligned Management
  • Resource Acquisition Management
  • Responsibility Accountability Matrix

3.
Question 3
When you use the RACI or Responsible, Accountable, Consult, Inform version of the RAM, those who are responsible are:

1 point

  • Not completing the work
  • Supervising the work
  • Completing the work
  • Providing subject matter expertise

4.
Question 4
A work package is a/an:

1 point

  • Activity that can be assigned to one or more organizational units
  • Deliverable at the lowest level of the WBS
  • Required level of reporting
  • Activity at the lowest level of the WBS

5.
Question 5
The WBS is used to derive all but one of the following:

1 point

  • The activity list
  • The project schedule baseline
  • The business need for the project
  • The project cost performance baseline

6.
Question 6
True or False: When it comes to projects, the emphasis is on strategic quality management. Quality is not an accident, quality is part of the plan, and quality is everyone’s job.

1 point

  • True
  • False

7.
Question 7
The discipline of quality management complements the discipline of project management. Both recognize the importance of:

1 point

  • Team satisfaction and inspection over prevention
  • Customer satisfaction, prevention over inspection, continuous improvement, and management responsibility
  • Company satisfaction, continuous improvement, and management protocol
  • Responsibility of only the sponsor, continuous improvement, and inspection

8.
Question 8
True or False: Product quality focuses on the project management processes used to meet project objectives

1 point

  • False
  • True

9.
Question 9
The Process Improvement Plan is:

1 point

  • The number one component of the project management plan.
  • a subsidiary, or component of the project management plan.

10.
Question 10
True or False: Performing quality assurance within the context of a project involves applying the planned, systematic quality activities to ensure that the project correctly employs all processes needed to meet project objectives and product requirements.

1 point

  • True
  • False
Module 3 Quiz

1.
Question 1
An estimate created by looking at a similar project or activity and then adding or subtracting to or from the estimate based on the differences between the two is called:

1 point

  • Exact estimating
  • Bottoms up estimating
  • Analogous estimating
  • Parametric estimating

2.
Question 2
When you have good historical information which can be used in a reliable formula or model, you will probably use:

1 point

  • Parametric estimating
  • Bottoms up estimating
  • Analogous estimating
  • Exact estimating

3.
Question 3
True or False: When you are concerned that your estimates might not be correct, especially if you think they are too low, you should pad the estimate and add extra.

1 point

  • False
  • True

4.
Question 4
Which one of these most correctly defines management reserve?

1 point

  • Management reserve is tied to specific work packages.
  • Management reserve is not tied to specific work packages it is for the entire project.
  • Management reserve is tied to a specific milestone or event.
  • Per our lesson, management reserve and contingency are exactly the same.

5.
Question 5
You are preparing an estimate of the cost for an IT system expansion for a new branch office location. It is a very similar to the IT system expansion undertaken for a branch office that opened six months ago. Which technique might you use if you are pushed for a quick estimate?

1 point

  • Analogous
  • Bottoms up
  • Parametric
  • Probabilistic

6.
Question 6
You are building an apartment complex with four, 10,000 square foot buildings based on the same drawings you used in another city two years ago. What is the danger of estimating using the same parametric model of $50 per square foot?

1 point

  • It’s not very easy to scale.
  • The technical design is unstable.
  • Historical cost relationships may no longer be applicable.
  • It will take much more time than a bottoms up estimating.

7.
Question 7
What description defines Bottoms Up Estimating?

1 point

  • A technique that involves estimating the cost of individual work packages or individual schedule activities with the lowest level of detail.
  • A technique that uses a mathematical model to estimate costs.
  • A technique that analyzes activities on past projects and using them as a basis for estimating costs.

8.
Question 8
True or False: The Project Budget is equal to only the cost baseline budget.

1 point

  • True
  • False

9.
Question 9
True or False: The S-Curve depicts the relationship between the cost baseline budget and the schedule because it shows the planned cost baseline budget across the planned project timeline.

1 point

  • True
  • False

10.
Question 10
Earned value management integrates scope, cost, and schedule measures to:

1 point

  • develop a preliminary budget.
  • assess project performance and progress.
  • assess communication effectiveness among project team members.
  • assess whether all requirements were met.
Module 4 Quiz

1.
Question 1
When you schedule work in a specific order because it cannot be completed any other way this is what type of dependency?

1 point

  • External
  • Discretionary
  • Internal
  • Mandatory

2.
Question 2
True or False: If develop online modules must be 100% completed before review online modules can begin, that is called a finish to start relationship.

1 point

  • False
  • True

3.
Question 3
If develop online modules needs to finish before review online modules can finish, that is called a:

1 point

  • Start to finish relationship.
  • Start to start relationship.
  • Finish to start relationship.
  • Finish to finish relationship.

4.
Question 4
To calculate early start (ES) and early finish (EF) perform a:

1 point

  • Critical pass
  • Lateral pass
  • Forward pass
  • Backward pass

5.
Question 5
True or False: The critical path is the shortest path through the network and represents the work that can be delayed without delaying the end of the project.

1 point

  • False
  • True

6.
Question 6
The network diagram is the best tool for demonstrating:

1 point

  • The sequence of project activities
  • Resource requirements
  • Schedule performance over time
  • Schedule variances

7.
Question 7
All of the following are inputs to estimating activity durations except:

1 point

  • Organizational process assets
  • Resource calendars and scope statement
  • Activity list and activity attributes
  • Requirements specifications

8.
Question 8
In a project schedule, the sequence of activities which cannot be delayed during the course of the project without extending the project end date is referred to as the:

1 point

  • Slack line
  • Schedule baseline
  • Critical path
  • Action plan

9.
Question 9
A significant event in a project that may indicate completion of a major phase is a/an:

1 point

  • Work package
  • Activity
  • Deliverable
  • Milestone

10.
Question 10
Once the logic of a network is laid out, the project manager will conduct a forward pass and a backward pass through the network. This will provide information regarding ______ and will identify the________.

1 point

  • The total duration of the project, critical path
  • The high risk activities, non-critical path
  • Resource shortages, high risk activities
  • The slack for each activity, high risk activities
Final Exam

1.
Question 1
True or False: The term resources only refers to people, it does not include money or materials or equipment.

1 point

  • True
  • False

2.
Question 2
In our lessons the acronym RAM stands for:

1 point

  • Responsibility Accountability Matrix
  • Resource Acquisition Management
  • Resource Aligned Management
  • Responsibility Assignment Matrix
  • Responsible Accountable Manageable

3.
Question 3
When you use the RACI or Responsible, Accountable, Consult, Inform version of the RAM, those who are responsible are:

1 point

  • Completing the work
  • Supervising the work
  • Providing subject matter expertise
  • Not completing the work

4.
Question 4
A work package is a/an:

1 point

  • Activity that can be assigned to one or more organizational units
  • Activity at the lowest level of the WBS
  • Deliverable at the lowest level of the WBS
  • Required level of reporting

5.
Question 5
The WBS is used to derive all but one of the following:

1 point

  • The project schedule baseline
  • The business need for the project
  • The activity list
  • The project cost performance baseline

6.
Question 6
True or False: When it comes to projects, the emphasis is on strategic quality management. Quality is not an accident, quality is part of the plan, and quality is everyone’s job.

1 point

  • False
  • True

7.
Question 7
The discipline of quality management complements the discipline of project management. Both recognize the importance of:

1 point

  • Team satisfaction and inspection over prevention
  • Customer satisfaction, prevention over inspection, continuous improvement, and management responsibility
  • Responsibility of only the sponsor, continuous improvement, and inspection
  • Company satisfaction, continuous improvement, and management protocol

8.
Question 8
The Process Improvement Plan is:

1 point

  • a subsidiary, or component of the project management plan.
  • The number one component of the project management plan.

9.
Question 9
An estimate created by looking at a similar project or activity and then adding or subtracting to or from the estimate based on the differences between the two is called:

1 point

  • Parametric estimating
  • Bottoms up estimating
  • Exact estimating
  • Analogous estimating

10.
Question 10
When you have good historical information which can be used in a reliable formula or model, you will probably use:

1 point

  • Parametric estimating
  • Bottoms up estimating
  • Analogous estimating
  • Exact estimating

11.
Question 11
True or False: When you are concerned that your estimates might not be correct, especially if you think they are too low, you should pad the estimate and add extra.

1 point

  • True
  • False

12.
Question 12
Which one of these most correctly defines management reserve?

1 point

  • Management reserve is tied to specific work packages.
  • Per our lesson, management reserve and contingency are exactly the same.
  • Management reserve is not tied to specific work packages it is for the entire project.
  • Management reserve is tied to a specific milestone or event.

13.
Question 13
You are preparing an estimate for the cost of an IT system expansion for a new branch office location. It is a very similar to the IT system expansion undertaken for a branch office that opened six months ago. Which technique might you use if you are pushed for a quick estimate?

1 point

  • Analogous
  • Probabilistic
  • Bottom up
  • Parametric

14.
Question 14
You are building an apartment complex with four, 10,000 square foot buildings based on the same drawings you used in another city two years ago. What is the danger of estimating using the same parametric model of $50 per square foot?

1 point

  • The technical design is unstable.
  • Historical cost relationships may no longer applicable.
  • It will take much more time than a bottom-up estimating.
  • It’s not very easy to scale.

15.
Question 15
What description defines Bottom-Up Estimating?

1 point

  • A technique that analyzes activities on past projects and using them as a basis for estimating costs.
  • A technique that uses a mathematical model to estimate costs.
  • A technique that involves estimating the cost of individual work packages or individual schedule activities with the lowest level of detail.

16.
Question 16
True or False: The S-Curve depicts the relationship between the cost baseline budget and the schedule because it shows the planned cost baseline budget across the planned project timeline.

1 point

  • False
  • True

17.
Question 17
When you schedule work in a specific order because it cannot be completed any other way this is what type of dependency?

1 point

  • Mandatory
  • Discretionary
  • Internal
  • External

18.
Question 18
If develop online modules needs to finish before review online modules can finish, that is called a:

1 point

  • Finish to finish relationship.
  • Start to start relationship.
  • Finish to start relationship.
  • Start to finish relationship.

19.
Question 19
To calculate early start (ES) and early finish (EF) perform a:

1 point

  • Backward pass
  • Critical pass
  • Forward pass
  • Lateral pass

20.
Question 20
True or False: The critical path is the shortest path through the network and represents the work that can be delayed without delaying the end of the project.

1 point

  • True
  • False

21.
Question 21
The network diagram is the best tool for demonstrating:

1 point

  • Schedule variances
  • Schedule performance over time
  • The sequence of project activities
  • Resource requirements

22.
Question 22
All of the following are inputs to estimating activity durations except:

1 point

  • Activity list and activity attributes
  • Resource calendars and scope statement
  • Organizational process assets
  • Requirements specifications

23.
Question 23
In a project schedule, the sequence of activities which cannot be delayed during the course of the project without extending the project end date is referred to as the:

1 point

  • Critical path
  • Action plan
  • Schedule baseline
  • Slack line

24.
Question 24
A significant event in a project that may indicate completion of a major phase is a/an:

1 point

  • Activity
  • Milestone
  • Work package
  • Deliverable

25.
Question 25
Once the logic of a network is laid out, the project manager will conduct a forward pass and a backward pass through the network. This will provide information regarding ______ and will identify the________.

1 point

  • The total duration of the project, critical path
  • The slack for each activity, high risk activities
  • Resource shortages, high risk activities
  • The high risk activities, non-critical path

Conclusion

Hopefully, this article will be useful for you to find all the Week, final assessment and Peer Graded Assessment Answers of Budgeting and Scheduling Project of Coursera and grab some premium knowledge with less effort. If this article really helped you in any way then make sure to share it with your friends on social media and let them also know about this amazing training. You can also check out our other course Answers. So, be with us guys we will share a lot more free courses and their exam/quiz solutions also and follow our Techno-RJ Blog for more updates.